[1] viXra:1008.0032 [pdf] submitted on 11 Aug 2010
Authors: Priti Singh, Florentin Smarandache, Dipti Chauhan, Amit Bhaghel
Comments: 10 pages
Crashing is a process of expediting project schedule by compressing the total project duration. It is helpful when
managers want to avoid incoming bad weather season. However, the downside is that more resources are needed to
speed-up a part of a project, even if resources may be withdrawn from one facet of the project and used to speed-up
the section that is lagging behind. Moreover, that may also depend on what slack is available in a non-critical
activity, thus resources can be reassigned to critical project activity. Hence, utmost care should be taken to make
sure that appropriate activities are being crashed and that diverted resources are not causing needless risk and
project scope integrity. In this paper we want to present a technique called "Unit Crashing" to reduce the total cost
of project. Unit Crashing means to crash the project duration by one unit (day) instead of crashing it completely.
This technique uses an iterative approach to perform unit crashing until all activities along the critical path are
crashed by desired amount. The output of this method will reduce the cost of project, and is useful at places where
cost is of major consideration. Crashing PERT networks can save a significant amount of money in crashing and
overrun costs of a company. Even if there are no direct costs in the form of penalties for late completion of projects,
there is likely to be intangible costs because of reputation damage.